AmerenUE has agreed to pay the Federal Energy Regulatory Commission (FERC) a US$10M civil penalty, to fund US$5M in improvements in the vicinity of the Taum Sauk project, and to adopt a comprehensive safety program for AmerenUE’s hydroelectric facilities.
The US$10M civil penalty is the largest the FERC has ever imposed in a hydroelectric matter. The penalty plus the US$5M in improvements are over and above the costs AmerenUE will incur in remediating the environmental and property damage caused by the breach.
‘The Commission’s [FERC] first duty in hydroelectric regulation is assuring safety,’ said FERC Chairman Joseph T. Kelliher. ‘This penalty should send a message to the industry that the Commission [FERC] expects strict adherence to its rules and regulations – particularly those involving public safety. The Taum Sauk event was very serious. AmerenUE has accepted responsibility for this incident and cooperated fully with Commission staff in our investigation.’
In the AmerenUE proceeding, FERC staff alleged that the company committed 15 violations of various FERC regulations and license conditions, including failure to notify the commission of conditions affecting the safety of the project and failure to use sound and prudent engineering practices. In entering into the settlement, AmerenUE neither admitted nor denied the alleged violations.
On 7 April, AmerenUE submitted a report prepared by an independent consultant it retained under a directive from the FERC, whose dam safety staff then conducted an exhaustive forensic investigation of the breach, which is detailed in a report released 28 April. Finally, a report by a team of independent experts assembled by FERC was released on 25 May.
On 14 December 2005, the northwest corner of the Taum Sauk project’s upper reservoir breached at approximately 05:20 CST (US Central Standard Time) after the reservoir was overfilled.
The breach released approximately 6.3B litres of water, which flowed through the Johnson’s Shut-ins state park and into the East Fork of the Black river, upstream from the project’s lower reservoir. The flood injured nine people and caused extensive environmental and property damage.
The FERC investigation found that the immediate cause of the breach was that water overtopped the dam. Transducers that measured the height of water pumped into the upper reservoir had become loose from their anchors and gave inaccurate readings, indicating reservoir levels were lower than actual levels. AmerenUE, which was aware of the transducer problem, made several adjustments to its instrumentation but had not repaired the transducers at the time of the breach. AmerenUE did not notify FERC of these developments.
AmerenUE agreed to pay a US$10M civil penalty immediately and to place US$5M in escrow for improvements at or near the Taum Sauk project, including implementation of an enhanced emergency management system for the area. AmerenUE must consult with and obtain Commission staff approval for all improvements.
Finally, AmerenUE agreed to adopt a comprehensive Dam Safety programme. Among other things, the programme creates a new position of Chief Dam Safety Engineer for both of AmerenUE’s Commission-licensed projects, who will serve as the central contact with the Commission for all safety and regulatory matters. The Chief Dam Safety Engineer also will have authority to shut down plant operations if safety is compromised.
Related ArticlesAmerenUE plans to rebuild Taum Sauk FERC clears Ameren to start Taum Sauk rebuild Taum Sauk reservoir breached State to investigate dam failure US governor calls for more dam control Consultant delivers Taum Sauk verdict Ameren management blamed over Taum Sauk failure