The works include rehabilitation of turbines, generators and associated equipment on the plant’s six units.
Ingra was the main contractor during the original construction of the Haditha project in the 1980’s.
Serving the hydro power and dam construction industries since 1949
Croatian civil engineering firm Ingra is to carry out construction work valued at EUR 5.8M as part of a major rehabilitation project at the 660MW Haditha hydroelectric project in Iraq.
The works include rehabilitation of turbines, generators and associated equipment on the plant’s six units.
Ingra was the main contractor during the original construction of the Haditha project in the 1980’s.