2002 REFURBISHMENT PROGRAMME...

1 January 2000


2002 REFURBISHMENT PROGRAMME...
Gross head Installed Annual
  (m) capacity (MW) output (GWh)
Aigas 18 20 60
Ceannacroc 90 20 87
Gaur 30 6 21
Invergarry 53 20 78
Orrin 222 18 80
Torr Achilty 16 15 42



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.