Arch dam - Features Dimension/Quantity Unit
Height 188 m
Crest length 420 m
Crest elevation 1,145 m
Maximum thickness at base 28 m
Thickness at crest 5.6 m
Low level outlet radial gates – 4 No. at el. 1,057m 8.0 x 5.6 m
Open excavation 310,700 m3
Underground excavation 14,800 m3
Concrete (mass and structural) 1,034,000 m3
Unit Cost of Concrete (incl. cement, not forms) $100.24 USD
Reinforcing steel 7,000 tonnes
Embedded cooling pipes 204,000 m
Concrete placement period 36 months
Maximum concrete placement rate 46,800 m3/month
Average concrete placement rate 28,700 m3/month
Cement Content (Dam mix including pozolans) 240 kg/ m3
Average dam concrete strength (150mm maximum aggregate mix - 97% std. dev.) 30.2 Mpa
Power Complex - Features Dimension/Quantity Unit
Intake structure height 75 m
Upper headrace tunnel, 7.25m lined diameter 320 m
Vertical shaft, 6.75m lined diameter 120 m
Lower tunnel 6.75m reducing to 4 - 4.0m steel lined penstocks 408 m
Powerhouse cavern 95lg x 18w x 38h m
Tailrace tunnels, 4 No. x 5m diameter x 73m long 292 m
Francis Turbines 4 ea
Plant Maximum Flow 220 m3/sec
Unit Design Head 155 m
River Diversion Works - Features Dimension/Quantity Unit
Diversion Tunnel No.1 – invert lined, dia. 7.8m 430 m
Diversion Tunnel No.2 – fully lined, diameter 7.0m 370 m
Upstream cofferdam – Mass concrete
Crest length 75 m
Top elevation 978.5 m
Height 18.5 m
Concrete Volume 10,443 m3
Tunnel No. 2- Duel High Pressure Bonneted Slide gates 2.54w x 2.67h m



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.