Project Name Location Dam height (m) Reservoir (km2) Size (MW) Cost (US$M) Status
Upper Kontum PoKo trib. 14 220 276 Planning  
Pleikrong PoKo trib. 65 80 110 256 Planning
Yali PoKo trib. 69 64.5 720 1000 Commissioned
Se San 3 Se San 73 6.4 273 283 Construction
Se San 3A Se San      100   Planning
Se San 4 Se San 60 54 330 280 Feasibility
Total       1753    



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.